Yesterday we were able to remove 5 of the old light poles between Catherine and Spring Street, with the cooperation of Duke Power. We continued the sewer behind the Police Station.
Today College Street on the North Side will be closed for the sewer tie-in to the sewer in the middle of the road. Because of the wet stone and conditions the asphalt process between Tugaloo and Catherine has been delayed until Monday. Curb positioning and elevation work will be going on between Catherine and Ann Streets on the North Side of main.
Hutch-N- Son Construction