Yesterday we tried hard to progress, but the weather is stronger than we are.
We did get a small driveway poured between Tugaloo and College. We also marked some demo marks between College and Spring on the North side of Main. We moved some traffic devices in place as you can see.
Today we hope to pour a couple more areas if weather permits.
We will also start demolition between North College and North Spring.
Electrical work is scheduled on some changeovers at College and Main.