Sorry Folks about the other E-Mails. There will not be a closing of the side parking lots at the corner of College and Main Monday and Tuesday.
I will not close them until Main is open and re-constructed in front of Martha’s.
We then will need to close them to change over the power to underground.
Those E-Mails were sent to the wrong address.
As you can see there is a lot of daily activity that has to happen to do this project.
Tugaloo to College: Curb Contractor mobilized yesterday.
Please be aware that there will be a lot more personnel working and trucks and activity will increase over the next few days.
Safety is always the most important.
Please look out for the workers.
College to Catherine: Electrical work on light pole bases and preparations for the curb crew to continue onto this block.
Hutch-N-Son Construction